Guide · Securities and dates

Bid security and bid validity, explained for contractors

A bid security is a guarantee you submit with your bid. It lets the employer claim the sum it states if you withdraw your bid while it is still valid, or if you win and then fail to sign the contract or provide the performance security. Bid validity is how long your offer stays open for the employer to accept. The security has to outlast the bid.

In World Bank-financed works tenders, the bid security must stay valid 28 days beyond the bid validity date (ITB 19.3 of the Bank's Request for Bids for works, September 2025 edition). This guide covers where those figures are set, the forms a security can take, bid-securing declarations, extension requests and the mistakes that get a security rejected, with a calculator for the dates. Rules are as of October 2026; your tender's Bid Data Sheet and addenda always decide.

Create your workspace Reviewed 09/10/26

Bid security, bid-securing declaration and performance security

Tenders use three related instruments, and confusing them can make a bid non-compliant.

InstrumentWhen you give itWhat it protects againstWhat it costs you if called
Bid security (tender security, bid bond, bid guarantee)With the bidA bidder who withdraws during validity, or wins and will not sign or provide the performance securityUp to the security's amount
Bid-securing declarationWith the bid, instead of a securityThe same failuresSuspension from bidding for that employer's contracts for the period the tender states
Performance securityAfter award, by a deadline counted from the letter of acceptanceThe contractor failing to perform the contractThe guarantee or bond amount, under the contract's terms

The environmental and social performance security

World Bank documents may also require a separate environmental and social (ES) performance security from the winner. The Bank's template contract data says it is normally 1% to 3% of the accepted contract amount, and that the two performance securities together should normally not exceed 10%. Those notes guide the employer; the figures in your tender's contract data are the ones that bind.

The forms a bid security can take

The World Bank's works document lets you choose among these forms, provided the security is a demand guarantee from a reputable source in an eligible country (ITB 19.3):

A non-bank issuer outside the employer's country needs a correspondent institution in that country to make the guarantee enforceable, unless the employer agrees in writing before submission that none is needed. A bank guarantee must use the bid security form in Section IV, or a substantially similar format the employer approved before submission. That form is subject to the ICC's Uniform Rules for Demand Guarantees (URDG 758).

  • an unconditional guarantee from a bank, or from a non-bank financial institution such as an insurance, bonding or surety company;
  • an irrevocable letter of credit;
  • a cashier's or certified cheque;
  • another security the Bid Data Sheet lists as acceptable.

Bid bond or bank guarantee?

Bid bond usually means a security from an insurer or surety, and bank guarantee one from a bank. The evaluator checks the issuer and the wording. The World Bank form commits the guarantor, irrevocably, to pay on the employer's complying demand, backed by the employer's statement that the bidder withdrew its bid or, once told it had won, failed to sign the contract or furnish the performance security. A bond that pays only once default is proved, or that adds conditions, may not comply. Give your issuer the tender's own form and ask for it word for word.

Where the amount and the validity are set

Both figures are in the Bid Data Sheet (BDS), against the Instructions to Bidders (ITB) clause they complete, and an addendum can change either. In the World Bank document, BDS ITB 19.1 says whether a bid security or a bid-securing declaration is required (never both) and gives the amount and currency, per lot where there are lots; one security may cover several lots for their combined amount. BDS ITB 18.1 gives the date until which bids must remain valid.

In World Bank and ADB documents the amount is a fixed sum the employer sets, not a percentage of your own price, so read how your own tender states it. Development-bank guidance keeps it modest: the Asian Development Bank's user guide to its standard bidding documents for goods says it is normally computed as 1% to 2% of the estimated contract value.

Current World Bank works documents state validity as a calendar date (BDS ITB 18.1), and the Bank's drafting note explains that a date not linked to the submission deadline reduces bidders' errors. Many other documents give a number of days counted from the deadline; ADB's goods guide says validity should normally be 90 days. Either way the period must allow the employer to evaluate, obtain approvals and any prior review by the financing bank, and award (World Bank Procurement Regulations, paragraph 5.39).

The security outlasts the bid so the employer has time to call it. The Regulations put that margin at generally four weeks beyond the validity period (paragraph 5.33), and the works document fixes it at 28 days beyond the original validity date or any extended date (ITB 19.3). Use the margin your tender states.

In the World Bank document, a bid that is not valid until the BDS date is rejected as nonresponsive (ITB 18.1), and so is a bid without a substantially responsive security or declaration (ITB 19.4). One day short is enough.

Bid validity and bid security date calculator

For a tender that states validity in days, enter the submission deadline, the validity days and the number of days the security must outlast the bid (28 in World Bank and ADB documents). The calculator shows the last day your bid and your security must each cover. It runs in your browser and stores nothing you type.

If your tender gives a validity date instead, as World Bank documents do, your security must run to that date plus the stated margin. Either way, ask your issuer for a fixed expiry date, not a duration it counts for itself.

The calculator counts calendar days from the deadline date, as the World Bank document does unless it says business days (ITB 1). If your tender counts differently, follow its wording, and give your issuer a date with a few days to spare: a few extra days rarely cause a problem, while a security that expires early can sink the bid.

Bid validity and bid security dates

Uses the tender’s own figures: take them from the Bid Data Sheet and the latest addendum. Nothing you type leaves this page.

Choose the deadline date and enter the validity days from the tender.

Counted in calendar days from the deadline date. If the tender counts differently, or the employer extends the validity period, its wording wins.

When the employer asks you to extend

Evaluations overrun, and an employer that cannot award before validity ends may ask bidders to extend. Under the World Bank document (ITB 18.2), the request must come before validity expires, and both the request and your reply are in writing. You may refuse without forfeiting your bid security; your bid then lapses. If you agree, you must extend the security to 28 days beyond the new validity date, and you may not change your bid except as ITB 18.3 provides.

If the award is delayed more than 56 days beyond the original validity date, a fixed-price contract is priced at your bid adjusted by a factor the BDS states, an adjustable-price contract is not adjusted, and bids are still evaluated on the unadjusted price (ITB 18.3). When a request arrives:

  1. 1Check that it names your RFB and lot, and note the new validity date and the security expiry it implies.
  2. 2Decide whether your prices, plant, people and subcontract quotes still hold for the longer period. Refusing only ends your chance at this contract.
  3. 3If you agree, ask your issuer for an amendment extending the security to the new date plus the margin, in the same form and wording.
  4. 4Reply in writing before the current validity expires, enclose the amended security if the employer asks for it, and keep proof of delivery.

When a security is called, and when it comes back

Under the World Bank document, a bid security may be forfeited in two situations (ITB 19.7):

The deadlines after award are short. The winner must sign the contract agreement within 28 days of receiving it and furnish the performance security within 28 days of the letter of acceptance; failing either is grounds to annul the award, forfeit the security and award the contract to the next most advantageous bid (ITB 48 and 49). Arrange your performance guarantee facility before you bid, not after you win.

A bid-securing declaration swaps money for exclusion: if you withdraw or modify your bid during its validity, or win and fail to sign or provide the performance security, you are suspended from bidding for that employer's contracts for the period the tender states (Procurement Regulations, paragraph 5.35). Not being under such a suspension is itself a qualification requirement in the Bank's document. Where no bid security is required, the BDS can also provide for the borrower to declare a bidder ineligible for the employer's contracts for a stated period after the same failures (ITB 19.9).

Unsuccessful bidders' securities are returned once the winner has signed the contract and furnished its performance security; the winner's comes back once it has done both (ITB 19.5 and 19.6).

  • you withdraw your bid before the validity date stated in your letter of bid, or any extended date you agreed;
  • you win and fail to sign the contract, or to furnish the performance security and any ES performance security the BDS requires.

Errors that get a bid security rejected

The security is checked with the technical part, before anyone reads your price, and a bid whose security or declaration is not substantially responsive is rejected (ITB 19.4). The defects are usually mechanical:

Some bidding documents let the employer ask for a compliant replacement within a short period: ADB's user guide for its goods bidding document gives Bid Data Sheet wording for this, with a period of generally 14 days. Do not plan on it. For the other ways bids fail, see why tenders are rejected.

  • Wrong amount or currency, or one security that does not cover every lot you bid for.
  • Short validity: worked out from the original deadline and not moved after an addendum changed the dates, or missing the margin beyond bid validity.
  • Wrong names: a beneficiary other than the employer named in the BDS, the wrong RFB number, or a joint venture's security in one partner's name instead of the JV's, or of all future partners if the JV is not yet formed (ITB 19.8).
  • Wrong wording: conditions added by the issuer, a conditional bond where a demand guarantee is required, or a bank's own format the employer did not approve before submission.
  • Unacceptable issuer: an institution outside the eligible countries, or a foreign non-bank issuer with no correspondent institution in the employer's country.
  • Wrong place or a copy: in a two-envelope World Bank bid the original security goes in the technical part (ITB 19.1).
  • The wrong instrument: a declaration where the BDS asks for a security, or the reverse.

How Bidligence reads and checks these terms

When Bidligence analyses a tender pack, it records the bid security as structured fields: whether one is required, its form, the amount or the percentage of the bid price, the currency, how long it must be valid, the acceptable issuers and any prescribed wording. Bid validity is recorded in days and checked in a separate key-dates pass, which reads the date-bearing lines of every document and, within a length budget, the amendments, notices and instructions, newest amendment first, and records the document and clause that set it. If neither reading finds a figure, a fixed rule reads it from the tender text and skips sentences about the security, so the rule does not mistake a security's 28 days beyond validity for the bid's own validity. Where your tender states a validity date, as World Bank documents do, check BDS ITB 18.1 against the analysis.

The Submission Guard turns the tender's mandatory documents, bonds included, into a checklist matched against your Evidence Vault. When a security is required, its pre-submission audit restates the form, amount and validity the analysis recorded and tells you to check them, and the wording, against the instructions. The audit does not compare the guarantee your bank issues with the tender's form, so that check stays with you. The same audit flags expired linked evidence, claims in generated documents still to be confirmed, and a deadline two days or less away.

When you review an addendum, Bidligence records changes to the validity and the security terms, moves the bid's deadline when the closing date changes, and adds new mandatory documents to the Guard. On a paid plan, the Cover Letter & Bid Form generator states your bid validity, and the Forms & Declarations generator drafts a form for each declaration the analysis lists, noting where the tender's own wording must be copied in. A new account's 500 welcome credits cover analysing a tender; see AI tender analysis for what else the analysis reads.

Questions

What is the difference between a bid security and a performance security?
A bid security comes with your bid and can be called if you withdraw during the validity period, or win and will not sign. A performance security is given by the winner after award and covers performance of the contract.
How long should a bid security be valid?
As long as the tender says. World Bank and ADB documents require 28 days beyond bid validity, or beyond any extended validity date.
What is a bid-securing declaration?
A signed statement used instead of a bid security. If you withdraw during validity, or win and fail to sign or provide the performance security, you are suspended from bidding for that employer's contracts for the period the tender states.
Can I refuse to extend my bid validity?
Under the World Bank's standard document, yes: refuse in writing and you keep your bid security, but your bid lapses. If you agree, you extend the security too and cannot change your bid.
Is a bid bond the same as a bank guarantee?
Both can serve as a bid security: a bid bond usually comes from an insurer or surety, a bank guarantee from a bank. World Bank documents accept either if it is an unconditional demand guarantee from an acceptable issuer.
How much is a bid security?
Whatever the tender states: World Bank and ADB documents set a fixed amount and currency in the Bid Data Sheet. ADB's guidance for goods suggests computing it as 1% to 2% of the estimated contract value.

Sources

Rules and portals change. Check the tender’s own documents and the official source before you rely on any of this.

Know the security terms before you call the bank

Upload the tender pack and Bidligence reads the bid security and the validity, and turns the mandatory documents into a checklist you work through before submission.