Guide · Development-bank tenders

World Bank bidding documents for works, explained section by section

For a World Bank-financed works contract priced on unit rates and tendered through international competitive procurement, the bidding document is normally the Bank's Standard Procurement Document (SPD) Request for Bids, Works, completed by the borrower. As of October 2026 the current English edition is dated September 2025: a two-envelope document with rated criteria, in three parts and ten sections.

In short: read Section I, the Instructions to Bidders, with Section II, the Bid Data Sheet, which completes and overrides it. Check you qualify under Section III before you spend money, complete every Section IV form, price against Section VII, and read the contract: FIDIC's 2017 Red Book as amended in Section IX. Clause numbers below are from the September 2025 edition with the SEA/SH disqualification mechanism, so check the date and title on your document's cover.

Create your workspace Reviewed 09/10/26

The rules behind the document

Procurement in World Bank investment projects follows the Procurement Regulations for IPF Borrowers, now in their seventh edition (September 2025). The edition that applies is set by the project's legal agreement and named in the Specific Procurement Notice, so a tender can follow an earlier one. International competitive procurement must use the Bank's SPDs; national competitive procurement may use the borrower's own documents if the Bank finds them acceptable (paragraph 5.24).

For a bidder, three rules stand out. Your rights and obligations are governed by the bidding document and the contract, not by the Regulations or the loan agreement (paragraph 2.1). Open international procurement allows at least 30 business days to prepare bids unless the Bank agrees otherwise (paragraph 5.36). And the Bank arranges publication of the Specific Procurement Notice on its website (paragraph 5.23).

Versions differ: one works SPD adds the Bank's disqualification mechanism for sexual exploitation and abuse and sexual harassment (SEA/SH) obligations on high-risk projects, Section III has texts for bidding with and without prequalification, and smaller contracts can use the Request for Bids for Small Works.

The three parts and ten sections at a glance

The Specific Procurement Notice is not part of the bidding document (ITB 6.2). The document itself, read with any addenda issued under ITB 8, is made up as follows.

SectionWhat it containsWhat you do with it
I. Instructions to Bidders (ITB)Standard rules for bidding, opening, evaluation and award, used without modificationLearn it once per edition
II. Bid Data Sheet (BDS)This tender's data for each ITB clauseExtract every entry; it prevails over the ITB
III. Evaluation and Qualification CriteriaRated criteria, financial evaluation and pass/fail qualificationTest your firm before you decide to bid
IV. Bidding FormsLetters of bid, technical schedules, qualification forms, security forms, bill of quantitiesComplete every form in its own format
V. Eligible CountriesCountries whose firms, goods and services are excludedCheck your firm and your suppliers
VI. Fraud and CorruptionThe Bank's fraud and corruption provisionsThey bind you and your subcontractors
VII. Works' RequirementsScope, specification, ES requirements, key personnel, drawingsPrice and plan against it
VIII. General ConditionsFIDIC's Red Book, second edition 2017, reprinted 2022 with amendments, by reference onlyObtain the FIDIC book
IX. Particular ConditionsContract Data, Special Provisions, fraud and corruption, ES reporting metrics; they prevail over the General ConditionsRead closely: the contract's real terms are here
X. Contract FormsAward notices, beneficial ownership form, contract agreement and the securitiesCheck you can provide each security

Where a copy you got elsewhere differs from what the employer issued, the employer's documents prevail, and the employer is not responsible for addenda you did not receive from it (ITB 6.3). Get the document from the employer.

Read the ITB and the Bid Data Sheet together

Each BDS entry is keyed to the ITB clause it completes: BDS ITB 18.1 gives the bid validity date, BDS ITB 19.1 the security or declaration, BDS ITB 32.2 the rated criteria and weightings. The BDS complements, supplements or amends the ITB and prevails where they conflict, and an addendum under ITB 8 can change either. Extract these first, because each can disqualify you or change your price:

  • the submission deadline and address, whether electronic submission is allowed (ITB 22.1), and the number of copies;
  • the validity date (ITB 18.1) and the security or declaration, with amount and currency (ITB 19.1); see bid security and bid validity;
  • the rated criteria, their weightings and the weight for cost (ITB 32.2, ITB 40.1 and Section III);
  • whether bidding is limited to prequalified bidders, the maximum number of joint-venture members, and any domestic preference;
  • the subcontracting limit and the parts open to specialised subcontractors;
  • the clarification address: the employer only has to answer requests it receives at least 14 days before the deadline (ITB 7.1);
  • any change to the default local-labour requirement (ITB 16.2).

Never answer the ITB's generic wording when the BDS says something different. The BDS wins, and an addendum beats both.

Two envelopes: how bids are opened, scored and awarded

Each bid goes in two sealed envelopes inside an outer one (ITB 11 and 21). The technical part holds the technical letter of bid, the security or declaration, the signatory's authorisation, the qualification documents, the technical proposal, the SEA/SH declaration and the local labour method statement. The financial part holds the financial letter of bid, with the price and any discounts, and the priced bill of quantities. Then:

  1. 1Technical opening. Technical parts are opened in public; financial parts stay sealed in the employer's custody (ITB 25).
  2. 2Technical evaluation. Responsiveness, eligibility and qualification are checked, then the technical proposal is scored against the BDS rated criteria (ITB 30 to 32).
  3. 3Notification. Bidders that failed are told why and get their financial envelopes back unopened after the contract is signed; the rest are told when the financial parts will be opened, at least 10 business days later (ITB 33).
  4. 4Financial opening and evaluation. Scores and prices are read out in public; errors are corrected, prices converted to one currency and any margin of preference applied (ITB 34 to 37), 7.5% for eligible domestic contractors in the Section III template.
  5. 5Combined score. The most advantageous bid is the substantially responsive bid with the highest combined technical and financial score (ITB 40 and 41). An abnormally low bid must be justified or is rejected (ITB 38); a seriously unbalanced one can be made to carry a performance security of up to 20% of the contract price (ITB 39).
  6. 6Award. A notification of intention to award is followed by a 10-business-day standstill (ITB 43 and 44). The winner submits the beneficial ownership form within 8 business days of the request, signs within 28 days and furnishes the performance security within 28 days of the letter of acceptance (ITB 48 and 49).

Qualification: what Section III asks you to prove

Section III contains all the criteria the employer may use; no others may be applied. Its pass/fail table states, for each requirement, whether a joint venture meets it with all members combined, with each member or with one member. The template's requirements:

Three rules catch contractors out. Amounts are stated in US dollars, at the rate on the last day of each calendar year for turnover and on the contract date for a single contract. Only your own firm counts: the Regulations exclude parent companies, subsidiaries, affiliates and subcontractors other than permitted specialised subcontractors (paragraph 6.27). And the document defines similarity, by size, complexity, method or technology. Check everyone in your bid against the Bank's list of debarred firms, then make a bid/no-bid decision before you price.

FactorWhat the template requiresForms
1. EligibilityNationality; no conflict of interest; not declared ineligible by the Bank; conditions for state-owned enterprises; not excluded by the borrower's law or a UN resolutionELI-1.1, ELI-1.2, letter of bid
2. Historical contract non-performanceNo non-performance through contractor default since a stated year; no suspension under a bid-securing declaration; still sound if all pending litigation is lost; no consistent history of awards against you; a declaration of ES-related suspensions, terminations or called securities in the past five years; no Bank SEA/SH disqualificationCON-2 to CON-4, letter of bid
3. Financial situation and performanceFinancial resources for the contract's cash flow, not counting advance payments; audited balance sheets; a minimum average annual construction turnoverFIN-3.1 to 3.4
4. ExperienceGeneral construction experience; a minimum number of similar contracts of a minimum value; experience in key activities; experience managing ES aspectsEXP-4.1, EXP-4.2 (a) to (c)
Personnel and equipmentA qualified contractor's representative and key personnel; access to the key equipment listedPER-1, PER-2, EQU

Environmental, social and local-labour requirements

Section VII's environmental and social (ES) requirements, labelled ESHS (environmental, social, health and safety) in older editions, come from the project's commitments under the Bank's Environmental and Social Framework and its SEA/SH obligations: health and safety, environmental protection, hazardous materials, site security, labour conditions and more.

In the bid they become documents the evaluators read: the ES management strategies and implementation plans (ES-MSIP), the code of conduct for contractor's personnel, the SEA/SH declaration and Form CON-3 on past ES performance. They bind after award too: the template says the contractor may not mobilise to site until the Engineer consents that these measures are in place. The contract data may add an ES performance security, normally 1% to 3% of the accepted contract amount.

The September 2025 edition adds a local-labour rule. Unless the BDS says otherwise, you must allocate at least 30% of the total labour cost under the contract to local labour and submit a Local Labour Method Statement, set out by skill category in full-time equivalents, which becomes part of the contract (ITB 16.2 and the Section IV form). It implements paragraph 5.54 of the Regulations' seventh edition, and ITB 15 tells bidders to take it into account when stating their local and foreign currency requirements.

Price the local-labour plan, not just the form: recruitment, training and supervision cost money. See how to price a BOQ.

The contract: FIDIC Red Book plus Particular Conditions

Section VIII incorporates, without printing them, the General Conditions of FIDIC's Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer (the Red Book), second edition 2017, reprinted 2022 with amendments, and says the original must be obtained from FIDIC. Buy it: you cannot price the risk in a contract you have not read.

Section IX prevails over those conditions. Part A, the Contract Data, sets the parties, the time for completion, the defects notification period (365 days in the template), the performance and ES performance securities, the contractor's total liability and more. Part B, the Special Provisions, amends FIDIC's clauses; Part C covers fraud and corruption; Part D sets ES metrics for progress reports.

Two contract points reach back into the bid. The technical letter of bid asks you to propose three potential members of the Dispute Avoidance/Adjudication Board, with their CVs. And the performance security, a demand guarantee or a bond from an issuer the employer accepts (ITB 49), must be one your bank or surety will issue, in the Section X form or another form acceptable to the employer.

Common pitfalls and a pre-submission checklist

Before you seal the envelopes, check each point against the document. For the wider list of reasons bids fail, see why tenders are rejected.

  • Every addendum is obtained from the employer and read: the technical letter of bid declares no reservations to the bidding document, addenda included.
  • The validity date in both letters of bid matches BDS ITB 18.1, and the security runs 28 days past it in the amount, currency, form and name the BDS requires.
  • Every Section IV form is in its own format and signed by the authorised person, with amended pages signed or initialled (ITB 20).
  • Your firm, each JV member and each specialised subcontractor meets the Section III columns that apply to it, with the forms to prove it, and none is on the Bank's debarment list.
  • The ES-MSIP, code of conduct, SEA/SH declaration, Form CON-3 and local labour method statement are in the technical part, and no price or discount is.
  • Envelopes are sealed and marked as ITB 21 requires, with the copies the BDS asks for.
  • If you win, you can furnish the performance security and the beneficial ownership form on time.

How Bidligence reads a World Bank tender

Bidligence's GLOBAL procurement profile is written for development-bank and multi-country tenders, and the analysis is told to use it for them; 21 regional profiles cover national systems. GLOBAL expects bidding under development-bank standard documents, naming the World Bank SPD for works, with strict eligibility, security and form compliance and debarment lists, and counts the FIDIC 2017 books and the World Bank Environmental and Social Framework among its standards.

Bidligence reads a tender pack in order of authority, newest amendment first, then the notices, instructions and data sheet, forms and bills, conditions and specifications; drawings and reference standards come last and are capped in length, and scanned pages are transcribed before the analysis runs. The analysis records the procurement framework, evaluation method and weighted criteria, pass/fail eligibility, the mandatory documents, the returnable schedules in the tender's own numbering, key personnel, the security and validity, ESG and local-content requirements, risk flags and questions for clarification.

From there, on a paid plan, the Compliance Matrix generator lists each mandatory requirement, document and key criterion with your Vault evidence or the action needed, and the Mock Evaluator scores your draft against the tender's weighted criteria and lists pass/fail issues separately. The Submission Guard checks the mandatory items against your Evidence Vault. None of it replaces reading the BDS: it gives you a list to read it against.

These are the development-bank and multilateral sources Bidligence reads for its tender feed, which comes with saved searches on the Free plan:

Sources that returned tender notices to Bidligence in the last 30 days. The list updates itself.

  • World Bank — Procurement Notices
  • UNDP — Procurement Notices
  • TED — EU Tenders Electronic Daily (CPV 45)
  • UNGM — UN Global Marketplace

Questions

What is the difference between the ITB and the Bid Data Sheet?
The Instructions to Bidders are the World Bank's standard text, used without modification. The Bid Data Sheet gives this tender's specifics against each ITB clause and prevails where the two conflict.
Which edition of the World Bank Procurement Regulations applies?
The one named in the project's legal agreement and stated in the Specific Procurement Notice. The current edition is the seventh, dated September 2025, but a tender can follow an earlier one.
What conditions of contract do World Bank works contracts use?
The General Conditions of FIDIC's Red Book, second edition 2017, reprinted 2022, amended by the Particular Conditions in Section IX. The FIDIC text has to be obtained from FIDIC.
What is the World Bank's 30% local labour requirement?
Under the September 2025 works SPD, bidders must allocate at least 30% of the total labour cost under the contract to local labour, unless the Bid Data Sheet says otherwise, and submit a Local Labour Method Statement.
How is the winning bid chosen?
Under the two-envelope works SPD, it is the most advantageous bid: the substantially responsive bid from a qualified bidder with the highest combined technical and financial score, weighted as the Bid Data Sheet states.
Can my parent company's experience count?
No. The Procurement Regulations exclude the qualifications of parent companies, subsidiaries and affiliates. Firms can combine qualifications as a joint venture, within the rules in Section III.

Sources

Rules and portals change. Check the tender’s own documents and the official source before you rely on any of this.

Read your next World Bank tender against a checklist

Upload the bidding document and its addenda, and Bidligence reads the deadline, validity, security, criteria, eligibility and the mandatory forms into an analysis and a checklist.

Cookies on Bidligence

We use strictly necessary cookies to keep you signed in, protect your account and take payments. With your permission we also remember interface preferences on this device — theme, language and the 3D view’s look. We use no advertising or analytics cookies. Cookie Policy