What should the software pull out?
At the least, it should list the items below. The reasons come from the World Bank's works document (September 2025 edition). Your own tender may word them differently, and its documents decide.
| Item | Why it matters |
|---|---|
| Closing date and time | A late bid is rejected and returned unopened (ITB 23). |
| Bid validity | A bid not valid until the stated date is rejected (ITB 18.1). |
| Bid security | The amount and currency are in the Bid Data Sheet. Where one is required, a bid without a responsive one is rejected (ITB 19). |
| Documents to submit | The bid has a technical part and a financial part. The list includes a letter of bid, priced BOQ, signing authority, qualification evidence and technical proposal (ITB 11). |
| Qualification and evaluation criteria | Bids are evaluated using the criteria and methods in Section III. |
| Clarification deadline | The buyer answers requests received at least 14 days before the deadline (ITB 7). |
| Site visit and pre-bid meeting | The Bid Data Sheet says if a meeting or visit is offered (ITB 7). |
| Addenda | An addendum becomes part of the bidding document (ITB 8). |